Mondelez

Installation

BTR was contracted by a local millwrighting firm to partner to complete the turn key installation of Zeppelin ingredient handling and batching system Mondelez foods in Toronto Ontario. The project included the installation of over 5,000 feet of conduit and nearly 25,000 meters of wire all installed according to best practices for food processing installations. All mounting, fastening and miscellaneous materials were stainless steel. The project included installing all the system instrumentation, scales and power wiring to all motive devices. The project was completed while working in harmony on a site with at least 4 other electrical contractors and approximately 500 tradesmen. The project ran for approximately 4 months with BTR’s onsite presence reaching 20 men at its peak.